banner

 

arrow Events
arrow Downloads
arrow Links
arrow BRITA in PuBs
arrow DEMOHOUSE
arrow ECO-BUILD
arrow ECO-CULTURE
arrow INTECO BUILD
arrow SARA
arrow SMART-ECO
arrow Contact
arrow Home

European Commission Sixth Framework Programme

 

ECO-CULTURE Results

The Royal Danish Playhouse, Copenhagen, Denmark

The ten design target values for the Royal Playhouse are shown in the table. The expected values are shown together with the actually achieved values. A comment indicates the status of the design target.

Target Expected Actual Comment
Overall
Total heating consumption 1530 MWh/year 1244 MWh/year Achieved.
Total electricity consumption 1131 MWh/year 1366 MWh/year The utilisation time is much larger than expected. Achieved if utilisation was as originally presumed.
Total energy consumption 2661 MWh/year 2610 MWh/year Achieved in spite of larger time of use.
Integrated climate belt energy storage
Utilisation of stored heat from heat pump 250 MWh/year   Compressor has been activated June 2009 as heat pump. Measurements are continued.
Heat pump and seawater cooling
Max. heat demand 1-1.5 MW 1.1 MW Achieved. Based on heating degree days.
Electricity consumption, heat pump 56 MWh/year Potential shown Basis for consumption has been shown.
Annual savings in CO2 76 % 71 % (potential) Potential has been proven based on measurement of sea water.
Optimised and intelligent controlled ventilation systems incl. BEMS
Heating consumption, ventilation 367 MWh/year 324 - 487 MWh/year Achieved when time of operation is over 4.5 hours a day for 150 days a year. This has been the case, so far.
Annual savings in CO2 49% 67% Achieved.
Environmentally friendly concrete
Savings in CO2 26%   Achieved.

The overall impression is that the targets have all been fulfilled or - in a few cases - the potential for fulfilling the target has been shown.
This is the case even in spite of a building that has turned out to be hugely successful in the first 1.5 year of operation, meaning that the time of operation has been much longer than expected. Thus, the electricity consumption related to especially ventilation, lighting and technical stage equipment has been larger.

Because of the complexity of the building, some of the systems have not functioned as designed during the initial phase of the life span of the building. This is the case for the cooling central, which has not yet reached its full potential, as the compressor units have only functioned as cooling machines and not as heat pumps. A flaw in the initial design of the cooling central has been changed, and the cooling central is now functioning to supply both heating and cooling to the thermo-active slabs. However, since only limited data exist, it has not been possible to show that the targets related to the cooling central have been met. Instead, the potential is shown by assessing the data that are available. Once the system has operated using the full potential in the cooling central, the energy consumption will drop to an even lower value than today.

Concerning heating energy, the building is using 19% less than expected. This is a big success and shows that the overall building design has a low requirement for heating.
Concerning electricity consumption, the building uses 23% more than originally expected. This is due to the fact that the time of use is over 40% longer than originally expected. If data are recalculated to the expected time of use, the building would have met the design target value.
Finally, it should be mentioned that the investigations made will lead to further energy savings, as several systems can be optimized to achieve even lower energy consumption. This is especially the case for ventilation and lighting. For further information see the Monitoring Report.

Amsterdam Library, The Netherlands

The library is extensively equipped with energy meters for heating, cooling, ventilation and electricity. The energy meters are connected to the BEMS and the building users have the possibility of surveying the energy consumption on an aggregated level through the BEMS. If necessary, a more detailed level is possible. At the present time, some corrections to the BEMs have to be made with respect to the correct presentation of the energy use. All facilities are installed, and the BEMS will become an important tool to reduce the energy consumption to a minimum.

photo_08

The principal flows of energy are the heat, cold and electricity usage. In the table underneath, the overall results for the year 2008 are presented.

Month
Heat
Cold
Electr.
 
GJ
MWh
GJ
MWh
MWh
Jan
901
250.3
206
57.2
311.129
Feb
700
194.5
159
44.1
288.161
March
805
223.6
186
51.7
275.200
April
456
126.7
181
50.3
292.182
May
282
78.3
748
207.8
295.449
June
135
37.5
376
104.4
329.348
July
133
36.9
698
193.9
314.407
Aug
101
28.1
771
214.2
332.116
Sept
259
71.9
435
120.8
372.835
Oct
475
131.9
274
76.1
359.303
Nov
803
223.1
263
73.1
377.073
Dec
1299
360.8
295
81.9
336.956
Total
6349
1764
4592
1275
3884.2

The data have not been corrected for degree days. These are the data on the meter level or so to say the level of the building. The data have to be calculated back to primary energy use. For the heat and cold, the Coefficient Of Performance (COP) has to be used to determine the primary energy use. For the electricity, the efficiency of the power generation in the Netherlands has to be taken into account. At this moment, a factor of 0.39 has been used. The COP and efficiency factors are in line with the factors used in the obligatory energy performance calculation. This calculation was made in order to get a building permit.

 

 
Meters
 

Primary energy

Design
 
GJ
ngen
GJ
MJ/m2
MJ/m2
Heat
6349
4.2 x 0.39
3876
139
118
Cold
4592
12
383
14
7
Electr.
12673
0.39
32494
1169
481
 Total
1322
606

The electricity use of the in house restaurant is estimated to be 364 MWh/yr and is subtracted because this was outside the original design.
Looking at the data in the tables, a number of observations and comments can be made immediately:

  • Heat and cold usage are within the target range. Additional cold usage can be explained by the larger electricity use and extra heat usage.
  • The target values for heating have been met. For cooling and electricity the values are higher than expected. The main deviation is the electricity use.
  • Electricity use is far off the expected value. Further analysis is necessary. This is currently under investigation.

The following table shows the planned and achieved energy consumptions and CO2 reductions.

Target Expected Actual Comment
Overall
Total heating consumption (HP) 1001 MWh/year 1044 MWh/year Achieved
Annual savings in CO2 23 % 15 % Achieved
Total electricity consumption cooling 54 MWh/year 64 MWh/year Achieved
Annual savings in CO2 67 % 60 % Achieved
BEMS advanced ventilation system incl. lighting
Total electricity consumption (prim.) 3714 MWh/year 9026 MWh/year Much larger time of use than expected
Annual savings in CO2 13 % - Not yet achieved
Solar PV systems
Total electricity production 55.5 MWh/year 57.6 MWh/year Achieved
Savings in CO2 33 ton 34 ton Achieved

Opera House, Oslo, Norway

The Opera House is one of Oslo's most famous tourist attractions and is therefore a perfect arena for demonstrating energy effective technologies.
The Opera House is extensively equipped with energy meters for heating, cooling, ventilation and electricity. The energy meters are connected to the BEMS, and the users have the possibility of surveying the energy consumption down to a detailed level through the BEMS. At the present time, the BEMS is not completely running, but is used. The BEMS has already proved to be an important tool to reduce the energy consumption to a minimum.

Corrected budget with respect to area:

 Year   2004 2009
 Area m2 35000 47000
[kWh/m².yr]  [kWh/year] [kWh/year]
Room Heating 37 1288000 1729600
Ventilation heating 34 1198718 1609707
Heating of hot water 10 350000 470000
Fans and pumps 41 1436914 1929570
Cooling (Compressors) 20 682500 916500
Humidifying 21 732153 983177
Light 11 393273 528109
Theatretechnical equipm 22 787116 1056984
Msc 18 645336 866594
   Sum 1-8 215 7514010 10090242
Outdoor area = 900 m2  
9 Outdoor snowmelting 3 90000 120857
   Sum 1-9 217 7604010 10211099

 

District heating 84 2926718 3930164
Electricity cooling 20 682500 916500
Electricity rest 114 3994792 5364435
Sum 217 7604010 10211099

In 2008, the energy consumption for the Opera House was 5 708 480 kWh from district heating and 9 712 245 kWh from electricity, which is much higher than the predicted. Calculations and measurements have been done to document the saving potential that is related to the operation of the technical plants in the Opera House. The results show that the energy savings potential at the Opera House are significant for both thermal and electrical energy.
According to calculations of a high and low energy budget, the biggest potential for reducing the energy consumption from district heating is related to ventilation, snow melting and room heating, respectively.
Simplified calculations considering running times of all the ventilation aggregates in the Opera House showed that the energy consumption can be reduced to almost 1/5 by changing operation conditions from continuously running of all aggregates on maximal capacity all year through to 10 hours' running a day, 5 days a week, with VAV systems running with an average capacity of 50 % during operation.

photo_09

The difference between the actual and the predicted electrical energy consumption can be explained by several factors: the original energy budget for electricity did not include energy consumption for conducting the restaurant, the workshops or the electrical snow melting system. These are all major posts regarding the electricity consumption. In addition, the bus system that is managing the light control has been out of function. The light has therefore been on continually in the main part of the building. The bus system is programmed these days, and the electrical energy consumption will most likely decrease significantly when the control system is running
The findings from the tests and monitoring lead to activities as described in chapter 3.5 performance tests during 2. and 3. quarter of 2009.
Results show that these tests lead to great improvements and reduction of energy consumption. The following figures show the monitored monthly total energy use and energy use for district heating in the opera house in 2008 and 2009.

photo_10

photo_11

Figure 3.27 District heating consumption in 2008 and 2009

Both figures show a remarkable change in energy use the second part of 2009. This change is a direct result of the improvement process that will continue.
The results show that we are now within ECO culture target for 2010 for heating and cooling.

photo_12

The solar cells on south façade of the Opera House have been running since 12 February 2009 and had produced 6112 kWh per 29 May. The solar panels had some reduced capacity due to problems with some inverters, only 22 kW was working properly a part of the year. This is now corrected. The expected production in 2010 is 16 % higher than the original budget. In addition to having a utilitarian value, the solar cells demonstrate to the public that the Opera House is focusing on renewable energy and is concerned with the environment.


 

ECO Budget Monitored 2009
After 12/2-09
Budget 2010
kWh kWh kWh
Solar cells 20 618 18000 24000

 

 

 

Co-ordination Contact

If you have any questions about our project, please contact:

Peter Weitzmann
Project Manager
Energy Department
Phone: +45 4597 2397
E-mail: pewe@cowi.dk

 

Project Website

 

Public Project Report

Legal Note & Imprint

Home